Sun Prairie Utilities
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
1. Parallel Generation (20 kW or less) - Net Energy Billing (see Pgs-1 Rate Schedule). Customers that qualify for this rate schedule are metered and billed under a net energy basis. The revenue meter records all energy delivered and all energy received from the DG facility during the billing period.
2. Customer-Owned Generation Systems (greater than 20 kW) - (see Pgs-2 Rate Schedule). Customers that qualify for this rate schedule are metered and billed for all energy consumed at their retail rate and receive a credit for all energy delivered to the utility. The revenue meter records all on/off peak energy delivered and all on/off peak energy received from the facility during the billing period.
- Rebates Offered
- 1
- Deregulated
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Supply Side Taps Allowed
- 0
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 20
- System Size Restriction Type
- AC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
The “20 kW” rating shall be the AC rating of the generator or inverter.
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
Street address of DG facility
Adjoining street name
Electric service entrance
Electric meter
Interface equipment
Location of major equipment
Location of interconnect disconnect switch (if required)
• System capacity must be 0.5 kWDC or greater.
• System must be installed within 90 degrees of due south. (Azimuth)
• Must be installed with a panel tilt between 10-50 degrees.
• Must have less than 10 percent obstacle shading based on analysis of an industry-accepted tool.
- SLD Reqs
Generator or inverter
Point where DG facility is electrically connected to the customer’s electrical system
Point of common coupling
Lockable interconnection disconnect switch (outside, if required)
Method of grounding, including generator and ]transformer ground connections
Protection function and systems
- Website
- link
- Phone
- (608) 837-5500
Other details
- Restrict Inspection
- 0
- Address ID
- 167988
- Express Planset Eligible
- Yes