Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Solar Export Type
- Avoided Cost
- Solar Export Rate Approx
- 0.0668
- Net Excess Generation Notes
The customer shall be billed monthly on a net energy basis and shall pay the fixed charge and energy charge specified in the rate schedule under which he is served. When the energy produced exceeds energy consumed for the billing month, the customer shall be credited for the excess energy volumes at the avoided cost rate in Pgs-2. Monthly credits shall be computed by taking the net excess kilowatt-hours produced times the sum of the applicable energy charge plus monthly power cost adjustment clause (PCAC)
NEM is does not vary based off of system size. 20kW or less and greater are both paid out at the utilities avoided cost of power.
- Rebates Offered
- 0
- Deregulated
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
System size = DC
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Meter Spot Process
Temporary Disconnect Reconnect Process (TDR) Email request and address to:
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
Must show location of external disconnect
- SLD Reqs
"Single Line Diagram Requirements. ANSI symbols shall be used in the one line schematic diagram to show the following:
• (a) Generator or inverter.
• (b) Point where the DG facility is electrically connected to the customer’s electrical system.
• (c) Point of common coupling.
• (d) Lockable interconnection disconnect switch.
• (e) Method of grounding, including generator and transformer ground connections.
(f) Protection functions and systems. "
- Placards
The applicant shall label the interconnection disconnect switch, “Interconnection Disconnect Switch”, by means of a permanently attached sign with clearly visible and permanent letters. The applicant shall provide and post its procedure for disconnecting the DG facility next to the switch.
Other details
- Restrict Inspection
- 0
- Express Planset Eligible
- Yes