Benton PUD

Washington Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

If the electricity generated by the Customer exceeds consumption and is distributed back to the PUD during the billing period, then the Customer shall be credited for the net excess kilowatt-hours generated during the billing period, with this kilowatt-hour credit appearing on Customer’s bill for the following billing period. Every year in March any remaining credits will be exhausted with no compensation to the member.

Rebates Offered
0
Deregulated
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Percentage
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
Yes
Production Meter Criteria

Production meter is OPTIONAL

  • Production meter base shall not be affixed to manufactured home or any temporary structure
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Standard

SLD Reqs

See SLD Example in files

Electric Service Reqs

AC Disconnect Required

  • Must be a UL listed AC disconnect switch
  • Must be a visible break and in the lockable open position
  • Must be located between the meter base and generating equipment

Production Meter Required (confirmed with utility 2/12/2024)

Placards

Common labeling, at Interconnection Customer’s expense, furnished or approved by the Utility and in accordance with NEC requirements must be posted on meter base, disconnects, and transformers informing working personnel that a generating facility is operating at or is located on the premises.


  1. PRODUCTION METER: AC production meter base shall be labeled, "CUSTOMER GENERATOR, PRODUCTION METER", with engraved phenolic placards; 3/8" white capitalized lettering on a red background.
  2. Main electric service (Net Meter) meter base shall be labeled "NET METER, CUSTOMER GENERATOR CONNECTED TO THIS SERVICE", with engraved phenolic placards; 3/8" white capitalized lettering on a red background.
  3. When the production meter is not within line of sight of the net meter, an engraved placard showing both meter locations shall be installed next to the production meter.
Electrical Stamp Required
0
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Website
link
Phone
(509) 582-1230

Other details

Restrict Inspection
1
Revision Required
1
Mod Swap Requires Planset
1
Address ID
4470592
Express Planset Eligible
No
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Benton PUD before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.