Virginia Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

In any billing period in which there is a billing credit, the customer shall be required to pay only the non-usage sensitive charges for that billing period which includes the customer charge. Any billing period credits shall be accumulated, carried forward, and applied at the first opportunity to any billing periods having positive net consumption. However, any accumulated billing credits remaining unused at the end of a net metering period shall not be carried forward to the next net metering period.


The value of excess generation calculated for billing credits by the Town shall be at the end of each billing period

Rebates Offered
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Tap Criteria

Please refer to AHJ Requirements

Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch

Plans & docs

Site Plan Reqs

Please refer to AHJ Requirements

SLD Reqs

Please refer to AHJ Requirements

Electric Service Reqs

Please refer to AHJ Requirements

Install Reqs

Please refer to AHJ Requirements

Placards

Please refer to AHJ Requirements

Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0

Other details

Express Planset Eligible
Yes