Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

City of Blanding

Utah Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

If the electricity generated by the Customer exceeds the electricity consumed by the Customer and is distributed back to the City during the billing period, then the Customer shall be billed and pay for the same customer service charge(s) as are applied to other like customers of the City absent the Net Metering Program; however, the Customer’s account shall be credited for the net excess kilowatt-hours generated during the billing period, with this kilowatt-hour credit appearing on Customer’s bill for the following billing period. The kilowatt-hour credit shall be calculated using the total number excess kilowatt-hours generated for the month multiplied by the City’s Low Load per kilowatt-hour cost or the rate established by the City Council at the time. Credits on the Customer’s account may only be applied toward kilowatt-hour usage, not toward customer service charges. Any and all of the kilowatt-hour electric energy credit remaining on the account at the time of the Customer’s April billing each year shall be set to zero, without further liability to the City.

Rebates Offered
0
Deregulated
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

10 kW (AC or DC) or 120% historical consumption whichever is less

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Rate Schedule Link
link
Website
link
Phone
(435) 678-2791

Other details

Restrict Inspection
0
Revision Required
0
Mod Swap Requires Planset
0
Address ID
2117179
Express Planset Eligible
Yes