Rusk County Electric Cooperative, Inc.

Texas Utility Interconnection & net metering rules
Net Metering Allowed0
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
0
TOU Utility
0
Post Solar Billing Method
Export Rate
Solar Export Type
Avoided Cost
Solar Export Rate Approx
0.066
Net Excess Generation Notes

The interconnection is to be made on the member’s side of the meter, where the member will have first access to their generated power. Whatever power is not used at the time of generation will go through the meter and on to the grid(excess generation). RCEC will buyback the excess generation at the wholesale rate that is set in our tariff and currently at $0.066 per kWh

Rebates Offered
0
Deregulated
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
50
System Size Restriction Type
DC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Residential: 15 kW


System can be sized over 15 kW up to 50 kW but will require additional engineering review.


No offset requirement as long as it does not trigger any transformer upgrade; if it does a system downsize will be required or a dedicated transformer upgrade will be required. Customer can also wait for the coop to update their infrastructure but will not be until 2030s

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

line side tap conductors must end in a breaker or fuses not in mlo lugs in the panel.

Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Website
link
Phone
(903) 657-4571

Other details

Restrict Inspection
0
Revision Required
0
Mod Swap Requires Planset
1
Address ID
121123
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Rusk County Electric Cooperative, Inc. before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.