Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

NVEC - Navasota Valley Electric Cooperative, Inc.

Texas Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

No credit is given to the customer for excess generation produced at the end of each month

Rebates Offered
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Customers need to know that if they generate more energy than they use there is no credit for the over generation.

Offset Calc Tool
N/A

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

The diagram shall include at a minimum, all major electrical equipment that is pertinent to understanding the normal and contingency operations of the DG Interconnection Facilities, including generators, switches, circuit breakers, fuses, protective relays and instrument transformers


Line side tap conductors must end in a breaker or fuses not in mlo lugs in the panel.

Install Reqs

a) The Member shall install a visible load break disconnect switch at the Member’s expense and to the Cooperative’s specifications.

b) The switch will be located so as to be readily accessible to Cooperative personnel in a location acceptable to both the Member and Cooperative.

c) The switch shall be a type that can be secured in an open position by a Cooperative padlock. If the Cooperative has locked the disco

Website
www.navasotavalley.com
Phone
(979) 828-3232

Other details

Restrict Inspection
0
Address ID
121108
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with NVEC - Navasota Valley Electric Cooperative, Inc. before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.