NBU - New Braunfels Utilities
Line Taps Allowed0
Load Taps Allowed0
Net metering & export
- TOU Utility
- 0
- Rebates Offered
- 1
Interconnection & taps
- Approval Req To Install
- Yes
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- 0
System size & offset
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
- 24 kW-DC for residential and/or 999 kW for commercial
- Offset Calc Tool
- N/A
Plans & docs
- Site Plan Reqs
- - Meters shall be readily accessible to NBU at all times - Meters shall not be located behind a fence
- SLD Reqs
- - Solar (DER) Meter Separate from Utility Meter - Service Split in the U J-Box or Double gang meter socket - GEC require #6 AWG min
- Electric Service Reqs
- - The Utility Site walk (Meter Spot) required for every project.
- Install Reqs
- - Service Shut down required for every installation - "Pedestal (If Required) mounted equipment may have a minimum height of 36 inches" - Generation and consumption meter socket 4 feet minimum and 6-speed maximum from the center of the socket to the final ground grade, when measured 3 feet in front of the socket
- Website
- link
- Phone
- (830) 608-6851
Other details
- Address ID
- 133346
- Express Planset Eligible
- Unknown