FELPS - Floresville Electric Light & Power System

Texas Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
Supply Side Taps AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
TOU Utility
Yes
Post Solar Billing Method
Net Metering
Rebates Offered
No

Interconnection & taps

Approval Req To Install
Yes
Supply Side Taps Allowed
No
Line Taps Allowed
No
Load Taps Allowed
No
Tap Criteria

Lineside interconnection is not allowed, it has to be on the load side on a dedicated breaker (Piecing tap not allowed).

Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
50
System Size Restriction Type
DC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

UP to 50kW

Offset Calc Tool
N/A

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

SLD Reqs
  • Meter Socket (required)
  • PV > INV > Disco > PM > MSP
  • No interior sub POI allowed
  • If POI is on the FELP pole (W/ transformer), PV Equipment required to be installed on rack 6ft away.
  • If it's on the customer-owned pole, can attach to the pole.
Electric Service Reqs

Note- 1: The customer shall provide and install a manual load break switch that provides a clear indication of the switch position at the Point of Interconnection to provide separation between the FELPS electrical system and the customer's electrical generation system. The connections shall be labeled FELPS and Solar both inside and outside of the box identifying where the connection comes from. The location of the disconnect switch must be approved by FELPS. The disconnect switch shall be easily visible, mounted separately from metering equipment, readily accessible to FELPS personnel at all times, and capable of being locked in the open position with a FELPS padlock.


Note-2: The location of the fused disconnect or breaker boxes must be approved by FELPS. The disconnect or breaker boxes shall be easily visible, readily accessible to FELPS personnel at all times, and capable of being locked open in a way that would protect FELPS personnel from accidental closing and re-energizing of the system while work is being done by FELPS personnel in the area.

Website
link
Phone
(830) 216-7000
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with FELPS - Floresville Electric Light & Power System before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.