Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

El Paso Electric (TX)

Texas Utility Interconnection & net metering rules
Net Metering Allowed1
Supply Side Taps Allowed1
Line Taps Allowed1
Load Taps Allowed1
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
Post Solar Billing Method
Net Metering
Rebates Offered
0
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
1
Supply Side Taps Allowed
1
Line Taps Allowed
1
Load Taps Allowed
1
Tap Criteria

Line side taps should be done in main service panel, not in junction box or gutter

Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Percentage
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
System Offset Notes
  • In order to qualify for Rollback net metering we cannot exceed 100% of the homeowner's annual consumption. If the homeowner decides to proceed with an oversized system, they will have to to proceed with a different net metering option.
  • https://solarium3.epelectric.com/DGInterconnection/Forms/TX.aspx - see snip in files \/ \/ \/
  • If existing usage is not available, build to contract
  • If existing usage is exceeding kwh production, build to contract
  • If existing usage is below kwh production, build to as close to existing usage without going over
Offset Calc Tool
PV Watts

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-PM-Disco-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch

Plans & docs

SLD Reqs

Relay Meter Orientation = Over/Under

  • Total estimated production be added to the ELD (include existing system production if applicable)
  • PRODUCTION METER IS REQUIRED ON ALL PROJECTS
  • PV meter to be within 5 ft of utility meter
  • Ubill holder must be listed on the SLD
  • If we do not have 12 months usage, build to contract
  • INV > TOP OF PM, OUT THE BOTTOM OF PM > AC > POI > Bottom of Utility Meter, top of utility meter to utility feed
  • Conductors/neutral feeding MSP must be drawn from the bottom of the utility meter. See "One Line Diagram Sample" in Files section of this page.
  • The breaker rating specified on the SLD must match the installed breaker.
  • Utility meter should be wired with top wires going to Utility Feed, and Bottom wires going to MSP.
  • Utility will install one Production Meter (PM) and one Utility Bidirectional Meter (UM). Existing and new solar installations must be metered by the same PM.
  • If a water heater meter exists, add this note to SLD: "Water heater will be rewired prior to field inspection.โ€ The water heater meter must be wired to the MSP before requesting field inspection.
  • Surge Protection is NOT Required "unless we are replacing existing MSP with New (MPU)" Do not include this otherwise on the Plans.
  • Section 230.67 of the new 2020 NEC requires the installation of a surge-protective device (SPD) for all dwelling unit service entrances. New and replaced electrical equipment and systems must incorporate Type 1 or Type 2 SPDs. Type 1 surge protective devices can be installed before the main disconnect in the load center, at the meter enclosure or on the load side of the main circuit breaker. Type 2 surge protective devices can only be installed on the load side of the main disconnect, attached directly to a circuit breaker. Often, new construction will install Type 1 surge protectors, while renovations will install Type 2 surge protectors, but both types will satisfy the new requirements.
  • As of July 1, 2021, this state uses the 2020 NEC. See "Surge Protection and NEC 2020" in Files section of this page.

EXISTING SYSTEMS

  • Systems to be combined, Only one Production Meter per project.
  • Show kW-DC size of existing, new and total systems on both site plan & ELD. See "System Size example" in Files section of this page.
  • Show estimated production of existing, new, and total systems. Ex below
  • "New expansion estimated annual production : xxxx kWh AC"
  • "Existing system estimated annual production : xxxx kWh AC"
  • "Total system estimated annual production : xxxx kWh AC"
Install Reqs

INV > TOP OF PM, OUT THE BOTTOM OF PM > AC > POI

Placards

See "Label Sample" in Files section of this page.

Electrical Diagram Notes

BATTERY JOBS: Include the mode of operation on the ELD.



  • If existing meter is to be opened (Line tap or MBE), existing meter must be rated for 200A or more
  • Must have 3ft clearance in from of main panel, we will need to relocate
  • /\ /\ If existing UG service, we will need a meter spot to grandfather existing location
  • Bubble meters not permitted, must upgrade if existing bubble meter or under 100A service



  • Electrical Review Team \/ \/ \/ \/ (if the meter needs to be unlocked/opened for MPU/Derate/battery work)
  • Meter needs to be 80ft or closer from utility pole (if closest point on home is not within 80ft, we need a utility engineer to give the okay on the service drop distance to be left as is or may be required to install a meter pole closer to their utility pole)
  • Meter cannot be under a porch nor service line crossing a roof less than 8ft in height (service line to roof) or 4ft in length
  • Weatherhead is to be 36 inches from roofline
  • Middle of meter bubble must be minimum 4ft, max 5ft 6inches
  • No embedded meters allowed (if opening meter, would need to bring this out)
  • In the event that there is a tree in the path of where the service line will be running through (overhead), this will need to be trimmed prior to the utility energizing the MPU
Website
link
Phone
(915) 877-3400

Other details

Restrict Inspection
0
Revision Required
0
Address ID
132432
Express Planset Eligible
No
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with El Paso Electric (TX) before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.