Comanche County Electric Cooperative Association

Texas Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedNo
Line Taps AllowedYes
Load Taps AllowedYes
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
No
TOU Utility
No
Post Solar Billing Method
Export Rate
Solar Export Type
Avoided Cost
Net Excess Generation Notes

CECA will reimburse members for energy “delivered to” CECA distribution system at the avoided cost of energy rate (ACER). The ACER is calculated based on the Cooperative’s wholesale electric energy provider’s monthly invoices. The Member’s compensation for the excess energy supplied to the Cooperative during the monthly billing period shall accumulate as a monetary credit to be applied to future energy purchases by Member.

Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
Yes
Load Taps Allowed
Yes
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
50
System Size Restriction Type
DC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Up to 50 kW (as long as it doesn't trigger any upgrades)

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

SLD Reqs
  • line side tap conductors must end in a breaker or fuses not in mlo lugs in the panel.
  • PV meter wired top toward inverter, bottom toward POI
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Website
link
Phone
(800) 915-2533

Other details

Revision Required
No
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Comanche County Electric Cooperative Association before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.