City of Castroville

Texas Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

If Customer’s electric installation produces excess electricity, City shall pay Customer for excess electricity at the City’s “avoided cost”. Customer’s excess electricity shall be carried over month to month as a credit; but, Customer shall be paid a refund when service is either discontinued or at the end of the City’s fiscal year. Credits shall not be carried over into another fiscal year or be transferrable.

Rebates Offered
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
20
System Size Restriction Type
DC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Website
link

Other details

Restrict Inspection
0
Address ID
1021790
Express Planset Eligible
Yes