Report a correction Net Metering AllowedNo
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo
Net metering & export
- Net Metering Allowed
- No
- NEM Type
- Monthly
- TOU Utility
- No
- Post Solar Billing Method
- Export Rate
- Solar Export Type
- Avoided Cost
- Net Excess Generation Notes
The City shall pay Customer for the “kWh Received” (energy received by the City’s Distribution System) at the “Avoided Cost of Generation Rate” ACGR). The ACGR is determined by the average per kWh City of Brenham | DG Guidelines Manual | Customer Agreement cost of wholesale generation costs for electric energy purchased by City from its wholesale electric energy provider(s). City reserves the right to amend the ACGR at any time.
- Rebates Offered
- No
Interconnection & taps
- Approval Req To Install
- Yes
- Line Taps Allowed
- No
- Load Taps Allowed
- No
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- No
System size & offset
- System Size Battery Included
- No
- System Size Includes Existing Systems
- No
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Interconnection Study (w/ fee) will be required for any of the following scenario:
- System over 20 kW AC
- If proposed generation system is expected to export more than 15% of total load on the feeder
- If proposed generation system contributes more than 25% of maximum possible short circuit current
- Offset Calc Tool
- N/A
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
Plans & docs
- Install Reqs
- Website
- link
Other details
- Revision Required
- No