Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

BTU - Bryan Texas Utilities

Texas Utility Interconnection & net metering rules
Net Metering Allowed1
Line Taps Allowed1
Load Taps Allowed1
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
TOU Utility
0
Post Solar Billing Method
Net Metering
Solar Export Type
Avoided Cost
Solar Export Rate
0.03
Solar Export Rate Approx
0.03
Solar Export Value Notes
Export rate = variable fuel rate
Net Excess Generation Notes

BTU pays solar customers with a generation capacity of less than 50 kW for kWh at the current fuel rate (approximately $0.03/kWh). This will show as a credit on the customer’s bill.

Rebates Offered
0
Allows Standby
0

Interconnection & taps

Approval Req To Install
No
Interconnection Level
3
Line Taps Allowed
1
Load Taps Allowed
1
Tap Criteria

TAPS

  • For a LST, conduit must be RMC from the AC disconnect to the POI
  • Label required on MSP stating that the installation is a LST
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

SLD Reqs


Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Website
link
Phone
(979) 821-5830

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
119191
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with BTU - Bryan Texas Utilities before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.