Report a correction Net Metering AllowedNo
NEM TypeMonthly
Supply Side Taps AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo
Net metering & export
- Net Metering Allowed
- No
- NEM Type
- Monthly
- Post Solar Billing Method
- Export Rate
- Solar Export Type
- Fixed kWh
- Solar Export Rate
- 0.04
- Net Excess Generation Notes
The cumulative kWh delivered to the member will be metered separately from the kWh received to the grid from the member. All delivered kWh will be charged according to the applicable rate schedule. Received energy for that billing period will be credited by an amount per kilowatt-hour at the Cooperative’s Value of Renewable Generation as determined in accordance with exhibit.
- Rebates Offered
- No
- Deregulated
- No
- Allows Standby
- Yes
Interconnection & taps
- Approval Req To Install
- Yes
- Supply Side Taps Allowed
- No
- Line Taps Allowed
- No
- Load Taps Allowed
- No
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 6
- System Size Restriction Type
- AC kW
- System Size Battery Included
- No
- System Size Includes Existing Systems
- No
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- Inverter Oversize Restrictions
- Yes
- System Offset Notes
Max size 6 kW AC, or 7 to 7.5 kW DC
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- SLD Reqs
All equipment, disconnect location, inverter source of power, the panels and their quantity.
- Install Reqs
No meter socket required. Utility installs a special meter in the existing meter base.
- Website
- link
- Phone
- (803) 754-0153
Other details
- Revision Required
- Yes
- Mod Swap Requires Planset
- Yes