Rhode Island Energy

Rhode Island Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Supply Side Taps Allowed1
Line Taps Allowed1
Load Taps Allowed1
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

For customers on Net Metering:

Excess generation at the end of each month is credited at the applicable retail electricity rate and rolled forward to future bills as a dollar credit. This credit rolls forward indefinitely to future bills but cannot be "cashed out".

For customers on the Feed in Tariff REG program:

All kWh produced by the solar system are paid at the applicable FIT rate. Credits are first applied to the customer’s bill. Any remaining credits are then paid to the customer monthly by check.

*Regrowth is a locked in rate for the term of the contract. Simplified applications (under 15kw) = $0.2775/kW for 15 years. Expedited applications (over 15kw) = $0.2615/kW for 20 years

Rebates Offered
0
Deregulated
1
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
2
Supply Side Taps Allowed
1
Line Taps Allowed
1
Load Taps Allowed
1
Tap Criteria
  • Only 1 disconnect is required as long as Fused Disco is outside and fully accessible.
  • Disconnect to be labeled "Service Equipment. Accessible and lockable" on Site Plan and SLD.
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
1

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Basis
Average
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Size Justification
Load Justification
System Offset Notes

NO MORE SIZING RESTRICTIONS IF BELOW 25KWAC


RI calculator is no longer required as of 11/18/2025

Offset Calc Tool
N/A

Metering & disconnect

Production Meter Required
Situational
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Utility Owned Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Meter Spot Process

Some AHJ does not allow the same utility work order# to cover the PV and MPU, please submit the Work Request form to request a new work order # for an MPU. Note: Due to the required service change for this program if your electrical meter is currently located inside it will need to be moved outside at your location to meet National Grid standards. Overhead Service Installations At the home, provide single service from the weatherhead to a multi-gang meter socket, for installation of the multiple meters required for RE-Growth. At the home, provide parallel services from the weatherhead to individual meter sockets, for installation of the multiple meters required for RE-Growth. Note: Installation of a single service from the weatherhead to a junction box mounted on the side of the house, which would subsequently serve individual meter sockets is not acceptable. Bifurcation of the service for the purposes of serving multiple meters related to RE-Growth is only acceptable at the weatherhead. Underground Service Installations Provide single service to house, which will feed a multi-gang meter socket, for installation of the multiple meters required for RE-Growth. Expansion joint is required for the feeder entering the meter socket, which is consistent with National Grid standard practice for meter installation. Note: Due to the nature of underground service installations, a multi-gang meter socket is the only acceptable means of installation.

Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • Be sure to show restricted accesses, fences, gates and access controls
  • Disconnect to be labeled "Service Equipment. Accessible and lockable" on Site Plan and SLD
  • Include make and model in all equipment descriptions (including but not limited to panels, micro/inverter(s), combiner, discos, meters).

Existing System

  • Rhode Island Energy does not allow combo plans, plans must be separate per project.
SLD Reqs

Relay Meter Orientation = Over/Under


  • Show operating phase/voltage/power (AC) ratings.
  • If a Production Meter is required, it must be labeled as "Utility-Owned Production Meter".
  • AC Utility Disconnect Switch must be located outside, always accessible.
  • Include make and model in all equipment descriptions (including but not limited to panels, micro/inverter(s), combiner, discos, meters). Note any meter numbers (if available). Which pieces of equipment are located inside? outside?
  • If post-install plans are adjusted to "as built", an Electrical EE stamp with date and signature is required on the revised SLD.

Battery Project

  • See Sample Battery SLD for requirements.
Electric Service Reqs

The switch shall be gang operated, have a visible break when open, be rated to interrupt the maximum generator output and be capable of being locked open, tagged and grounded on the Company side by Company personnel.

Electrical Stamp Required
1
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Cover Page Notes

Battery [STORAGE CHARGING CAPABILITY: GENERATION ONLY // STORAGE DISCHARGING CHARACTERISTICS: ON-SITE LOAD ONLY]

Electrical Diagram Notes

Battery [STORAGE CHARGING CAPABILITY: GENERATION ONLY // STORAGE DISCHARGING CHARACTERISTICS: ON-SITE LOAD ONLY]

Website
link

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
126663
Express Planset Eligible
No
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Rhode Island Energy before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.