Net Metering AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
No
TOU Utility
No
Post Solar Billing Method
Feed-in-Tariff
Solar Export Type
Other
Solar Export Value Notes
Power Supply rate (.068549)
Net Excess Generation Notes

The Net Excess Generation Policy is only intended for residential properties that are owner occupied and single family, not to exceed a three family home.

The customer will receive an electric bill each month for the home's electric usage. The utility will take the kilowatt hours that the solar system produced and multiply it by their Power Supply rate (.068549) and apply a credit to the customer's bill. If the credit is maintained for two or more annual reconciliations, the customer can request the credit to be issued in the form of a check from the utility. The Power Supply rate is subject to change annually.

Rebates Offered
No
Deregulated
Yes

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Tap Criteria
  • Meters shall be connected to the "line side" of the PUD
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
10
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Offset Calc Tool
N/A

Metering & disconnect

Production Meter Required
Yes
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • AC disconnect is required to be installed within 10 feet of the production meter. Exterior locations only.
  • AC disconnect must be accessible to the utility 24/7
SLD Reqs
  • Requires a production meter
  • The production meter should not run through the utility meter and must be separate
  • Battery Projects: Require a whole home disconnect with the intention of the battery supplying power to the home in the case of a power outage
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Website
link
Phone
(401) 568-6222

Other details

Revision Required
No
Mod Swap Requires Planset
Yes