Net Metering Allowed1
NEM TypeAnnual
Supply Side Taps Allowed0
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
TOU Utility
1
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Members in this rate schedule shall sign a “Net Metering Agreement” with the Cooperative. Generally, the foregoing rates are net and are due and payable on or before the 10th of the month following the mailing date of the bill. Failure to receive a bill shall not release the consumer from liability of payment.


Account credits may be paid monthly by the Cooperative on or before the 10th of the month following the date of the bill or accrued for a 12- month period ending in March and refunded directly to the member.

Rebates Offered
0
Deregulated
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
0
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
1

System size & offset

System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Nameplate generating capacity of not more than twenty-five (25) kilowatts located on your premises

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

SLD Reqs


Install Reqs

"Member-generator shall furnish and install, on its side of the meter, a

disconnecting device capable of fully disconnecting and isolating the Net-Metering Facility (i.e. inverter system) from the Cooperative’s electric supply system. The disconnecting device shall be located adjacent to the Cooperative’s bi-directional metering equipment and shall be

of the visible break type in a metal enclosure that can be secured by a Cooperative owned padlock."

Equipment Approvals
California Energy Commission
Website
link
Phone
(503) 429-3021

Other details

Restrict Inspection
0
Address ID
282094
Express Planset Eligible
Yes