Wasco Electric Cooperative

Oregon Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

The charges for electric power and energy received by the member shall be those shown in the applicable retail rate schedule assigned, including the specified basic charge. In addition to the applicable retail rate class basic charge, a customer receiving service under this schedule #60 will be charged an additional net-metering basic charge of $5.00 per month and may incur an annual inspection fee if applicable.


The credit for any excess generation shall be disbursed every 12 months ending December 31, or more frequently if determined by the Cooperative. The Cooperative addresses this value by crediting the Customer’s account with its annual avoided energy cost which is the average cost of power (kwh) and demand (kw) to the cooperative.

Rebates Offered
0
Deregulated
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Nameplate generating capacity of not more than twenty-five (25) kilowatts for residential accounts.

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

WEC approved switching equipment capable of isolating the net metering facility from WEC’s system shall be provided by the member-generator and shall be located within 10 feet of WEC’s meter and accessible by WEC personnel.

Install Reqs

Customer shall furnish and install, on its side of the bidirectional meter, a safety disconnect device capable of fully disconnecting and isolating the Facility from Co-op’s electric supply system. The disconnect device shall be located adjacent to Co-op’s bi-directional meter and shall be of the visible break type in a metal enclosure that can be secured by a padlock

Placards

State of Oregon Standards

Equipment Approvals
California Energy Commission
Website
link
Phone
(541) 296-2740

Other details

Restrict Inspection
0
Address ID
284166
Express Planset Eligible
Yes