Net Metering Allowed1
NEM TypeMonthly
Supply Side Taps Allowed0
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Net Metering
Solar Export Type
Avoided Cost
Net Excess Generation Notes

OTEC shall allow Net Metering Facilities to be interconnected to OTEC facilities using a standard meter capable of registering the bidirectional flow of electricity. OTEC shall not charge the Member Generator separately for the bidirectional meter. OTEC may at its own expense install one or more additional meters to monitor the flow of electricity in each direction.

All net energy generated in excess of Member’s monthly net energy consumption and supplied to OTEC’s electrical supply system shall be valued at OTEC’s avoided cost. Excess usage does not roll month to month.

Rebates Offered
0
Deregulated
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
0
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
25
System Size Restriction Type
DC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Members generating not more than 25kW

Metering & disconnect

Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • The disconnect switch must be readily accessible to OTEC at all times and located within 10 ft. of OTEC's meter.
  • If the AC disconnect is not next to the utility meter (different structure, not in the line of sight, and etc.). A site map placard is required to show the location of the AC disconnect and the relation/distance of the AC disconnect from the meter.
SLD Reqs
  • Production Meter not required.
  • The disconnect switch must be a lockable, load-break switch that plainly indicates whether it is in the open or closed position.
Install Reqs

Installation of an automatic parallel generation disconnect safety switch is required on all net metering installations.

Placards

"Parallel Generation Onsite" metal or plastic engraved signage posted as required by the latest edition of the NEC. Permanent plaque that diagrams the location of the disconnect switch must be permanently installed adjacent to the meter.

Equipment Approvals
California Energy Commission
Website
link
Phone
(541) 573-2666

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
658350
Express Planset Eligible
Yes