Public Service Company of Oklahoma (PSO)
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
If you delivered more energy to PSO than you used during the month (measured in kilowatt-hours, or kWh), PSO will show the excess kWh on that month’s bill. After the calendar month is complete and SPP publishes their LMP prices, PSO will calculate the average price for that month (when your energy was produced), and you will receive the credit amount on your next month’s bill.
Avoided cost changes monthly or as needed.
- Rebates Offered
- 0
- Deregulated
- 0
- Allows Standby
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 1
- Load Taps Allowed
- 0
- Tap Criteria
Piercing connectors are not allowed. Utilize the IT-350 Polaris lugs connections for the LST
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- Percentage
- Offset Value
- 125
- Offset Calculation Basis
- Historical
- Offset Calculation Period
- 12
- Industry Standard Watts Sqft
- 2
- System Offset Notes
System must be sized as accurately as possible. Maximum offset is 125% of their historical loads. If it goes over 125% then they will not be eligible for the Net Energy Billing Option.
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- Yes
- Production Meter Position
- Inv-Disco-PM-POI
- Production Meter Labeling
- Production Meter
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Visible Lockable Labeled Disconnect
- Allowed Meter Adapter
- ConnectDER
Plans & docs
- Site Plan Reqs
Include spec sheets for any existing modules and existing inverters.
Disconnect must be within 10 feet of the main utility meter.
BOS ELEVATION:
- Needs to be drawn from a Site Audit picture of the actual site (See Elevation Drawing Example in files section below), hand drawn/MS paint drawings not acceptable.
- Equipment cannot be under an accessible window
- PM Meter should be 4 ft min and 6ft max from grade.
- Conduit runs need to be shown on elevation drawing.
- For LST add tap box.
- Show the dimension of each piece of BOS equipment from relative grade
- Conductors from Hoffman box to PV AC Disconnect shall be treated as service-entrance conductors and shall be as short as possible
- SLD Reqs
Relay Meter Orientation = Under/Over
Production Meter Required
- All meter sockets will be ringless style.
- Meter socket must be from the "AEP EastMeterSocket 10-30-2021" list which is attached in the Files Section below
- Show PM wired in from the top and out from the bottom
- Production meter must show bottom lugs going to inverter and top lugs to the POI. See example in files section.
Order of Equipment
- For Battery Backup systems with BUI/GW/SC - Inverter/Combiner > BUI/GW/SC > non-fused AC disconnect > PV meter -> MSP/MPI > utility meter.
- For PV Only and Non-backup Breaker Tie In - Inverter>Non fused AC Disconnect>Production Meter>POI
- For LST - Inverter>Non Fused AC Disconnect>Production Meter>Fused AC Disconnect>POI
Taps
- Line Side Taps allowed
- Piercing Tap Connectors not allowed. Use Polaris Taps with service rating stamped on the device
- Electric Service Reqs
Electric Service Requirements - Requirements For Electrical Service (aepnationalcustomers.com)
- Install Reqs
Production Meter Socket Required -
- Must have a barrel lock provision
- The meter must be wired so that energy production flows through the meter
AC Disconnect Required
- Must sit 48" to 66" above ground level
- Placards
AC Disconnect Placard Required:
- "Caution Generation Utility AC Disconnect"
- Electrical Stamp Required
- 0
- Equipment Approvals
- California Energy Commission
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Rate Schedule Link
- link
- Website
- link
- Phone
- (614) 716-2080
Other details
- Restrict Inspection
- 0
- Revision Required
- 1
- Mod Swap Requires Planset
- 1
- Address ID
- 4025169
- Express Planset Eligible
- No