Cookson Hills Electric Cooperative, Inc

Oklahoma Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedYes
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Solar Export Type
Avoided Cost
Net Excess Generation Notes

The value of that amount of electric energy delivered by Member-Generator to Cooperative’s system in excess of

the amount of electric energy delivered to the Member-Generator by the Cooperative shall be determined by

multiplying the number of excess kWh delivered by Member-Generator to Cooperative by the average monthly

avoided fuel cost of Associated Electric Cooperative, Inc. (AECI) during the billing period. The Member-Generator

shall receive credits equal to the value of the electric energy delivered to Cooperative. Credits will be applied to the

next billing period following issuance of the credits. The credits shall expire without any compensation at the earlier

of either twelve months after their issuance or when the Member-Generator disconnects service or terminates the

net metering relationship with Cooperative. Member-Generator agrees that credits will be applied to the billing

statement for the meter location to which the Member-Generator system is connected.

Rebates Offered
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
Yes
Load Taps Allowed
No
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
10
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A

Plans & docs

Website
link
Phone
(180) 032-8236