Washington Electric Cooperative (OH)
Spot something wrong?
Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.
Report a correction Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes
Net metering & export
- TOU Utility
- No
- Post Solar Billing Method
- Export Rate
- Solar Export Type
- Avoided Cost
- Solar Export Rate Approx
- 0.077
- Solar Export Value Notes
- Should the co-generation credit exceed the current month’s Distribution Energy Charges and Generation & Transmission Charges, then the remaining balance is forwarded on to be used on future m
- Rebates Offered
- No
- Deregulated
- Yes
Interconnection & taps
- Approval Req To Install
- Yes
- Line Taps Allowed
- No
- Load Taps Allowed
- No
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- No
System size & offset
- System Size Restrictions
- 25
- System Size Restriction Type
- DC kW
- System Size Battery Included
- No
- System Size Includes Existing Systems
- No
- Offset Type
- Combination
- Offset Value
- 100
- Offset Calculation Basis
- Historical
- Offset Calculation Period
- 12
- Industry Standard Watts Sqft
- 2
- System Offset Notes
25 kW or 100% offset whichever is less.
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- No
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Visible Lockable Labeled Disconnect
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
Must show location of the following:
- inverter
- PV panels
- meter
- accessible disconnect switch
- SLD Reqs
Standard
- Electric Service Reqs
A disconnect switch to isolate the DR equipment is required. The switch must be clearly labeled as a DR disconnect switch
PV W/ BATTERY:
If the customer connects a backup generator directly to the customer’s wiring to serve any load on the customer’s site, it shall utilize a double-throw transfer switch in order to ensure that no power is fed back onto the Cooperative’s distribution system. This is a critical safety requirement.
- Equipment Approvals
- California Energy Commission
- ESID Num Req SLD 3LD
- No
- Rate Schedule Link
- link
- Website
- link
- Phone
- (740) 885-5941
Other details
- Revision Required
- Yes
- Mod Swap Requires Planset
- Yes