Ohio Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

If the facility feeds more kWh back to the City than the City supplies to the customer, at the same site, during the billing period, then 50% of the excess kWh will be given as a kWh for the beginning of the next billing period. At no time will the consumer be entitled to, nor compensated for, any monetary payout of the excess electricity fed back to the city.

Rebates Offered
1
Deregulated
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Percentage
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Standard

SLD Reqs

Standard

Electric Service Reqs

The disconnect switch must be a lockable, load-break switch that plainly indicates whether it is in the open or closed position. The disconnect switch must be readily accessible to Napoleon Utility personnel at all times and located within 10 feet of the meter. The disconnect switch may be located more than 10 feet from the billing meter provided that permanent instructions are posted at the meter indicating the precise location of the disconnect switch.

Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
1
ESID Num Req SLD 3LD
0
Website
link

Other details

Address ID
2682817
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with City of Napoleon before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.