Butler REC (OH)
Net metering & export
- Post Solar Billing Method
- Export Rate
- Solar Export Type
- Avoided Cost
- Solar Export Rate Approx
- 0.052
- Net Excess Generation Notes
Net metering will be accomplished using a single meter or pair of meters capable of registering the flow of electricity in each direction from the Power Company Distribution System to Consumer’s electric consuming facilities located on the Premises, and from Consumer’s Electric Generating Facility to the Power Company Distribution System.
The Consumer shall use the output of the Electric Generating Facility first to meet the requirements of Consumer’s electric consuming facilities located on the Premises. The Power Company shall use an instantaneous kWh net billing period to measure the Consumer’s net production. The net production output shall be measured by determining during each such period the production in kilowatt-hours (kWh) of the Electric Generating Facility in excess of the requirements of the Consumer’s electric consumer facilities. Any such output of the Electric Generating Facility in excess of the requirements of Consumer’s electric consuming facilities shall be sold to Buckeye Power, Inc. The Power Company shall bill the net electric usage pursuant to the Power Company’s applicable Net Billing Rate Schedule, and credit the net electric output at Buckeye’s purchase rate, on a dollar for dollar basis.
- Rebates Offered
- 0
- Deregulated
- 1
- Allows Standby
- 1
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- 1
System size & offset
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
The Consumer’s “annual electric energy requirements” shall be the average amount of electricity consumed annually by the Consumer for the electric consuming facilities located on the Premises over the previous three years, using the annual period of June 1 to May 31.
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- SLD Reqs
One-line diagram showing the configuration of the proposed DR system, including the protection and controls, disconnection devices, nameplate rating of each device, power factor rating, transformer connections, and other information deemed relevant by the DR owner and/or the Cooperative.
- Placards
Switch must be clearly labeled as a DR disconnect switch.
- Equipment Approvals
- California Energy Commission
- Website
- link
- Phone
- (513) 867-4400
Other details
- Restrict Inspection
- 0
- Address ID
- 647983
- Express Planset Eligible
- Yes