Net Metering Allowed1
NEM TypeMonthly
Supply Side Taps Allowed0
Line Taps Allowed1
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Customer-Generators of electricity are eligible to be billed on a "standard net metering" basis. "Standard net metering" means measuring the difference in an applicable billing period between the electricity supplied by the Company and the electricity generated by a Customer-Generator that is fed back to the Company. Standard net metering shall be accomplished using a single meter capable of registering the amount (flow) of electricity which flowed in each direction during a billing period.


If the Customer-Generator provides more electricity to the Company than the Company provides to the Customer-Generator, only the excess generation component shall be allowed to accumulate as a credit until netted against the Customer-Generator’s bill, or until the Customer-Generator requests in writing a refund that amounts to, but is no greater than, an annual true-up of accumulated credits over a 12 month period. Bill charges or credits will be in accordance with the Generation Standard Offer Service Schedule that would apply if the Customer were not a Customer-Generator.

Rebates Offered
0
Deregulated
1
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
0
Line Taps Allowed
1
Load Taps Allowed
0
Tap Criteria

Taps allowed, tap box required.

Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Percentage
Offset Value
120
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
Inverter Oversize Restrictions
1
System Offset Notes

120% of historical usage

Offset Calc Tool
PV Watts

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

A one-line diagram showing the configuration of the proposed DG system, including the protection and controls, disconnection devices, nameplate rating of each device, power factor rating, transformer connections, and other information deemed relevant by the Interconnection Service Customer

Electric Service Reqs

AES requires an MPU permit for MPU work

Install Reqs

A disconnect switch to isolate the DG equipment for purposes of safety during maintenance and during emergency conditions. The Company may require a disconnect device to be provided, installed by, and paid for by the customer, which is accessible to and lockable by Company personnel, either at the primary voltage level, which may include load-break cutouts, switches and elbows, or on the secondary voltage level, which may include a secondary breaker or switch. The switch must be clearly labeled as a DG disconnect switch.

Placards

AC Disconnect must be labeled "DG DISCONNECT SWITCH".

Equipment Approvals
California Energy Commission
Website
link
Phone
(800) 433-8500

Other details

Restrict Inspection
0
Address ID
299369
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with AES Ohio (Dayton Power and Light) before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.