Springer Electric Cooperative
Net Metering Allowed1
Line Taps Allowed0
Load Taps Allowed0
Net metering & export
- Net Metering Allowed
- 1
- Post Solar Billing Method
- Net Metering
- Rebates Offered
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
- A site map or sketch needs to clearly show the location of all interconnection equipment, disconnect switches, meters and turbines/panels as well as structures and nearby roads/intersections, utility service pole(s) and utility transformer.
- SLD Reqs
- A one-line electrical diagram of the facility and its interconnection to the utility system needs to clearly show the electrical components, protective devices, manufacturer model numbers and electrical ratings. Indicate the model number and ratings of turbines/panels, batteries, inverters, fuses, circuit breakers, disconnect switches and meter housings.
- Install Reqs
- Interconnection customer understands and agrees to abide by the requirements of NMPRC Rule 568 for interconnecting generators sized no larger than 10 kW and using a certified inverter at the point of interconnection with CNMEC. Interconnection customer also agrees to abide by the Terms and Conditions for Interconnecting an Inverter-Based Generating Facility No Larger than 10 kW contained in the New Mexico Interconnection Manual, Exhibit 3A.
- Website
- link
- Phone
- (575) 483-2421
Other details
- Restrict Inspection
- 0
- Address ID
- 149742
- Express Planset Eligible
- Yes