CDEC - Continental Divide Electric Cooperative

New Mexico Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

"Utility may install an additional meter to measure separately the energy generated by the Producer and then calculate net energy consumed or supplied by the Producer. The Producer will be paid for energy supplied above the amount consumed at Utility’s energy rate for such purchases, as filed with the approved by the NMPRC. Utility will be paid for energy consumed by the Producer in excess of the amount supplied by the Producer at its approved tariff rate applicable to the service provided to the Producer. An additional customer charge to cover the added costs of

billing and administration may be included in the tariff."

Rebates Offered
0
Deregulated
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Percentage
Offset Value
120
Offset Calculation Basis
Historical
Offset Calculation Period
36
Industry Standard Watts Sqft
2
System Size Justification
Load Justification
System Offset Notes

We recommend you have the member request a three year history to calculate the size

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • The plans need to be signed by a Professional Engineer licensed in New Mexico
SLD Reqs

Showing the automatic disconnect

Electric Service Reqs

in compliance with current National Electric Code, State of New Mexico Building Codes and CDEC standards

Install Reqs

The Producer shall furnish, install and maintain a clearly labeled load break disconnect switch in avisible outside, readily accessible location for the purpose of isolating Producer’s generation fromthe Utility’s system. The load break disconnect switch must disconnect the Producer’s generator from the Utility’s system without interrupting other types of service to the Producer. The Producer shall provide a map of suitable scale showing the exact location of the switch. Such map shall be asecurable type switch. Ingress and egress to this switch by G&T’s or Distribution Cooperative’spersonnel shall be provided at all times by the Producer. The load break disconnect switch mustcomply with the interconnection and Safety Standards attached as Exhibit D hereto and incorporated herein by reference. 

Electrical Stamp Required
1
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Rate Schedule Link
link
Website
link
Phone
(505) 285-6656

Other details

Restrict Inspection
0
Address ID
148538
Express Planset Eligible
Yes