Report a correction Net Metering AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo
Net metering & export
- Net Metering Allowed
- No
- Post Solar Billing Method
- Export Rate
- Solar Export Type
- Avoided Cost
- Solar Export Rate Approx
- 0.06
- Net Excess Generation Notes
Per utility "our AMI meters have 2 channels, CH1 Delivered CH2 Received, and if there was ever a delivered read then that would be applied as bill credit. NEG credit amount is $0.06 per kWh"
- Rebates Offered
- No
- Deregulated
- No
Interconnection & taps
- Approval Req To Install
- Yes
- Line Taps Allowed
- No
- Load Taps Allowed
- No
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- No
- System Size Includes Existing Systems
- No
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
Plans & docs
- Website
- link
- Phone
- (919) 965-9841