Net Metering Allowed1
NEM TypeAnnual
Supply Side Taps Allowed1
Line Taps Allowed1
Load Taps Allowed1

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Net excess generation carries over monthly as a bill credit at the retail rate but is then forfeited with no compensation paid at the end of the annual true-up period

Rebates Offered
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
1
Line Taps Allowed
1
Load Taps Allowed
1
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
100
System Size Restriction Type
DC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes


Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Website
link
Phone
(910) 892-8071

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
177314
Express Planset Eligible
Yes