French Broad EMC

North Carolina Utility Interconnection & net metering rules
NEM TypeAnnual
Supply Side Taps Allowed0
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

NEM Type
Annual
Post Solar Billing Method
Export Rate
Solar Export Type
Fixed kWh
Solar Export Rate
0.04
Net Excess Generation Notes
  • Facilities not in excess of 20 kW

Customers will be credited monthly for the kilowatt hours generated and recorded on the meter provided. The credit will be calculated by determining the number of kilowatt hours generated multiplied by the cooperative’s residential generation rate. If member accumulates an annual credit greater than $50, a payment will be made to member in May of each year.

Rebates Offered
0
Deregulated
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
0
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
20
Automatic Transformer Upgrade Size Type
DC kW

System size & offset

System Size Restrictions
20
System Size Restriction Type
DC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Residential Solar limit is 20kW DC nameplate.

If you push the 20kW limit, the transformer may need to be upgraded and that would cost approx.. $2000.00. With roughly 300 systems we haven’t had to upgrade a residential transformer to accommodate solar. Almost all of the residential solar is less than 10kW.

Metering & disconnect

Meter Spot Process
  • PTO sent to Customer and Installer
  • The licensed electrician must call the local office for permission to pull the meter if needed. If they fail to do so and pull a meter without prior permission, the member will incur a $100 meter tampering fee. If the transformer needs to be relayed both off and subsequently back on, the member will incur two regular service call fees at $85 each. This is very rarely needed.
  • ETA of notice required for request: 24 hours
  • Who can schedule? Does not matter
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

Production Meter not required.

Need to see entire electrical path from the array to the grid. We do require a pull-down disconnect close to the meter base. If meter is pole-mounted away from the house, we will have to discuss.

Equipment Approvals
California Energy Commission
Rate Schedule Link
link
Website
link
Phone
(828) 649-2051

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
161446
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with French Broad EMC before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.