CHEC - Cape Hatteras Electric Cooperative
Net metering & export
- Net Metering Allowed
- 0
- NEM Type
- Monthly
- Post Solar Billing Method
- Export Rate
- Net Excess Generation Notes
We offer two ways to meter a solar array on Hatteras Island. The member can have the array metered separately from the house and sell 100% of the energy to CHEC at the wholesale rate. Right now that is around 3.5 cents/kwh. The more popular choice is to meter the array through the existing meter and use what they produce to offset their monthly bill. With this option, they are getting the retail rate (around 14.5 cents/kwh) but we do not compensate for any excess that is put back on the grid.
- Rebates Offered
- 0
- Deregulated
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
If the system is more than 25kW, you will be put in touch with our statewide G&T, North Carolina’s Electric Cooperative and will be required to sign an agreement with them.
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- Install Reqs
Member shall install a manual load-break disconnect switch with a clear visible indication of switch position between Cooperative’s electric system and Member’s Generator. The Isolation Device shall be installed as specified in the Interconnection Standard.
- Placards
Member shall install a permanent warning label in a conspicuous place in close proximity to the electric meter or on the meter base to notify them personnel that there is a generator installed on the load side of the meter. The warning label shall not be placed in a location that would interfere with the ability of Cooperative personnel to read the electric meter. Member shall also place a warning label on the Isolation Device. Cooperative will provide the
warning labels to Member. The warning labels must be in place before the Generator can be interconnected with Cooperative’s system.
- Equipment Approvals
- California Energy Commission
- Website
- link
- Phone
- (252) 995-5616
Other details
- Restrict Inspection
- 0
- Revision Required
- 1
- Mod Swap Requires Planset
- 1
- Address ID
- 160966
- Express Planset Eligible
- Yes