Yellowstone Valley Electric Cooperative
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Annual
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
After each monthly billing cycle, any excess kilowatt-hours generated are placed into a bank on the customers electric account. Based on the energy usage, banked kilowatt-hours will automatically be deducted from the account up to April 1
- Rebates Offered
- 0
- Deregulated
- 1
- Allows Standby
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- 0
System size & offset
- System Size Restrictions
- 10
- System Size Restriction Type
- DC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
100% offset or 10 kW DC (whichever is less). System may not exceed 10 kW DC but may exceed the 100% offset reasonably.
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- No
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Utility Disconnect Switch
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
- Disconnect switches near the meter are required. If it cannot be installed near the meter, a mapping placard of its location is required.
- SLD Reqs
Standard
- Electric Service Reqs
AC Disconnect Required
- Accessible, visible and lockable disconnect switch is to be provided by the member in an appropriate curcuit which is lockable in the open position only.
- Must be located at the members electric meter
- Clearly marked "Generator Disconnect Switch"
- Install Reqs
- Powering a system (including testing) is NOT permitted before we program (cogen) the meter , this will result in a tampering and meter fee.
- Placards
AC Disconnect:
- Clearly marked “Generator Disconnect Switch” on a weather resistant placard.
- Electrical Stamp Required
- 0
- Equipment Approvals
- California Energy Commission
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Website
- link
- Phone
- (406) 348-3411
Other details
- Restrict Inspection
- 1
- Revision Required
- 1
- Mod Swap Requires Planset
- 1
- Address ID
- 4777895
- Express Planset Eligible
- Yes