Glacier Electric Cooperative

Montana Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Glacier Electric utilizes an annual true up on December 31st of each year. Power generated in excess of the actual load at the location will not be purchased by the cooperative or credited to the meter after the annual true up period. Excess generation will be credited at the avoided cost (not provided)

Rebates Offered
0
Deregulated
1
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
1

System size & offset

System Size Restrictions
15
System Size Restriction Type
AC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Inverter Oversize Restrictions
0
Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch
Allowed Meter Adapter
None

Plans & docs

Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Website
link
Phone
(406) 873-5566

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
13379632
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Glacier Electric Cooperative before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.