Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

Three Rivers Electric Cooperative

Missouri Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Net Metering
Solar Export Type
N/A
Net Excess Generation Notes

The value of that amount of electric energy delivered by Member-Generator to Cooperative’s system more than the amount of electric energy delivered to the Member-Generator by the Cooperative shall be determined by multiplying the number of excess kWh delivered by Member-Generator to Cooperative by the average monthly avoided fuel cost of Associated Electric Cooperative, Inc. (AECI) during the billing period. The Member Generator shall receive credits equal to the value of the electric energy delivered to Cooperative. Credits will be applied to the next billing period following issuance of the credits. The credits shall expire without any compensation at the earlier of either twelve months after their issuance or when the Member-Generator disconnects service or terminates the net metering relationship with Cooperative. Member-Generator agrees that credits will be applied to the billing statement for the meter location to which the Member-Generator system is connected. 

Rebates Offered
0
Deregulated
0
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
100
System Size Restriction Type
AC kW
System Size Battery Included
1
System Size Includes Existing Systems
1
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Inverter Oversize Restrictions
0

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Rate Schedule Link
link
Website
link
Phone
(573) 644-9000

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
14367730
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Three Rivers Electric Cooperative before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.