Wellesley Municipal Light Plant
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Annual
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Rebates Offered
- 0
- Deregulated
- 1
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 10
- System Size Restriction Type
- AC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
If our proposed system is too large, they will demand that we downsize, it wouldn't be optional (regarding transformer upgrades)
Metering & disconnect
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
refer to pg 3-4 on DG Policy
the Utility Meter is outside. If it is inside, we will need to relocate it outside.
- SLD Reqs
They require a customer-owned production meter socket to be installed
refer to pg 3-4 on DG Policy
- Website
- link
- Phone
- (781) 431-1019
Other details
- Restrict Inspection
- 0
- Address ID
- 124418
- Express Planset Eligible
- Yes