Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
TOU Utility
0
Post Solar Billing Method
Net Metering
Rebates Offered
0
Deregulated
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
10
System Size Restriction Type
AC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

If our proposed system is too large, they will demand that we downsize, it wouldn't be optional (regarding transformer upgrades)

Metering & disconnect

Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

refer to pg 3-4 on DG Policy

the Utility Meter is outside. If it is inside, we will need to relocate it outside.

SLD Reqs

They require a customer-owned production meter socket to be installed

refer to pg 3-4 on DG Policy

Website
link
Phone
(781) 431-1019

Other details

Restrict Inspection
0
Address ID
124418
Express Planset Eligible
Yes