Taunton Municipal Lighting Plant

Massachusetts Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed1
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

If the electricity generated by the Customer exceeds consumption and is distributed back to TMLP during the billing period, then the Customer shall be billed for the same monthly service charge as applied to other customers of the TMLP in the same rate class; not be charged any kilowatt hours taken from TMLP and shall be credited for the net excess kilowatt hours generated as applied to the generation and Power Cost Adjustment (PCA) charges during the billing period; with this kilowatt-hour credit appearing on Customer’s bill for the following billing period.

(Consumption from TMLP) - (Excess Generation put onto the TMLP Grid*) - (PCA Cost) + (TMLP Monthly Service Charge) = Your Invoice Amount *Excess generation is credited at the ‘generation charge’ for your rate. Please see TMLP rate sheets for the exact amount: https://www.tmlp.com/electric/rates/

Rebates Offered
0
Deregulated
0
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
1
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

Include metering points in relation to TMLP's Electrical system and the customer's generating system location.

Placards


Electrical Stamp Required
0
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Site Plan Notes


Electrical Diagram Notes

All Jobs [AC Disconnect will be no further than 4′ from utility meter]

Website
link
Phone
(508) 824-3177

Other details

Restrict Inspection
0
Address ID
125065
Express Planset Eligible
Yes