Eversource Energy (Eastern MA)
Spot something wrong?
Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.
Report a correction Net Metering AllowedYes
NEM TypeMonthly
Supply Side Taps AllowedYes
Line Taps AllowedYes
Load Taps AllowedYes
AC Disconnect RequiredYes
Net metering & export
- Net Metering Allowed
- Yes
- NEM Type
- Monthly
- TOU Utility
- No
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
Excess generation at the end of each month is credited at the applicable retail electricity rate and rolled forward to future bills as a dollar credit. This credit rolls forward indefinitely to future bills but cannot be "cashed out".
- Rebates Offered
- Yes
- Deregulated
- Yes
- Allows Standby
- Yes
Interconnection & taps
- Approval Req To Install
- Yes
- Supply Side Taps Allowed
- Yes
- Line Taps Allowed
- Yes
- Load Taps Allowed
- Yes
- Automatic Transformer Upgrade Size
- 20
- Automatic Transformer Upgrade Size Type
- kW AC
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- Yes
- System Size Includes Existing Systems
- No
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- Inverter Oversize Restrictions
- No
- System Offset Notes
Metering & disconnect
- Production Meter Required
- Situational
- Production Meter Criteria
Production Meter (SMART meter)
- Required for: Cash, Loan, Aura, Aura+
- Not required for: Lease projects
- Wire inverter on bottom side and utility on top side
- Only 1 production meter per project
- Second meter allowed only if 12 months have passed since existing system PTO
- Production Meter Position
- Inv-Disco-PM-POI
- Production Meter Labeling
- Production Meter
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Visible Lockable Labeled Disconnect
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
- Show parcel boundaries (property/lot lines).
- Show distance from UM to Eversource Transformer in feet..
- Include Peak/Max Output
- SLD Reqs
- Projects over 15 kW AC require an EE stamp.
- Specify make and model of equipment. Do not use โMin 60Aโ for a disconnect size.
- Load Side Tap does not require 2 disconnects as long as Fused Disconnect is accessible outside.
- Include Peak/Max Output
- Electric Service Reqs
- Follow meter wiring and labeling guidelines..
- Allowable Meter Sockets:.
- Will require a meter relocation whenever the utility meter is located on the interior, or in any cabinets
- Max allowable height for the utility meter is 5'5" from grade, measured from the center of the meter.
- Electrical Stamp Required
- No
- Meter Num Req SLD 3LD
- No
- ESID Num Req SLD 3LD
- No
- Site Plan Notes
All Jobs [AC Disconnect shall be 24/7 accessible, within 10 feet of, within visible sight of, and on same wall as the Utility Meter (Exception for pedestal meters)]
- Website
- link
- Phone
- 413-787-1087
Other details
- Revision Required
- Yes