CWLP - City Water Light & Power
Spot something wrong?
Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.
Report a correction Net Metering AllowedYes
NEM TypeAnnual
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes
Net metering & export
- Net Metering Allowed
- Yes
- NEM Type
- Annual
- TOU Utility
- No
- Post Solar Billing Method
- Net Metering
- Solar Export Type
- Fixed kWh
- Net Excess Generation Notes
CWLP provides the customer full retail rate for all solar production through the use of a net meter. If the array is producing more power than is needed in the building, the net meter increments in reverse. If the array produces more electricity than the building consumes during the billing period the customer is billed for zero (0) kWh and the excess is saved for future use. All saved excess production is lost after the March billing cycle every year.
- Rebates Offered
- Yes
- Deregulated
- Yes
- Allows Standby
- Yes
Interconnection & taps
- Approval Req To Install
- Yes
- Line Taps Allowed
- No
- Load Taps Allowed
- No
- Tap Criteria
- CWLP doesn’t allow the use of insulation piercing connectors (Load/Line taps)
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 25
- System Size Restriction Type
- AC kW
- System Size Battery Included
- No
- System Size Includes Existing Systems
- No
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- Offset Calc Tool
- N/A
Metering & disconnect
- Production Meter Required
- Yes
- Production Meter Position
- Inv-PM-Disco-POI
- Production Meter Labeling
- Production Meter
- AC Disconnect Required
- Yes
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
- AC disconnect must be accessible to the utility 24/7
- Production meter required. Must be from the approved list of meters.
- SLD Reqs
Meter Orientation = Over/Under
- USE PV METER MODEL: MILBANK U6193-RL-QG-AMS SINGLE PHASE NEMA 3R 600V/100A FORM 2S MILBANK 6193 125A RINGED BIDIRECTIONAL PV PRODUCTION METER
- INV ----> TOP PM ---> BOTTOM PM --> DISCO ---> POI
- Example line diagrams are attached to database files
- Bond the neutral and ground in the main service.
BATTERY
- Utility requires push button DC disconnect: EA-353-359MFG: Square D, Control Station, Mushroom Push Button, Turn Release, 10A, Nema 4X, MFG SKU: XALK178
- Meter Num Req SLD 3LD
- No
- ESID Num Req SLD 3LD
- No
- Electrical Diagram Notes
All Jobs [AC disconnect must be accessible to the utility 24/7]
- Website
- link
Other details
- Revision Required
- No
- Mod Swap Requires Planset
- Yes