Net Metering Allowed1
NEM TypeAnnual
Supply Side Taps Allowed0
Line Taps Allowed1
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
Post Solar Billing Method
Export Rate
Solar Export Type
Avoided Cost
Solar Export Rate Approx
0.051
Solar Export Value Notes
Changes annually or as needed
Net Excess Generation Notes

If the amount of electricity produced by the Member exceeds the amount of electricity used by the Member during any point in time, the cooperative will provide a bill credit in an amount equal to .051 $/kwh for each kilowatt of energy supplied to the Cooperative. The rate will be evaluated annually corresponding with changes to energy and demand costs of the cooperative.


This bill credit will sum during the Applicable Billing Period and be provided as a credit to that bill. In the event the credit exceeds the Members cost of energy for the Applicable Billing Period the Minimum Monthly Charges will apply.

Rebates Offered
0
Deregulated
0
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
0
Line Taps Allowed
1
Load Taps Allowed
0
Tap Criteria
  • Please note that we do not allow floating type connectors to be used, including taps in the MSP or meter can, an exterior mounted accessible disconnect needs to be added, and finally the meterbase will need to be a lever-by-pass style.
  • Taps must be in a tap box
  • Taps required unprotected production meter which comes before the fused disconnect
  • See "Tap Example" in files section below
  • Any MPU, sub panel, or tap will require a whole house disconnect
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
25
System Size Restriction Type
AC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Size Justification
Load Justification
System Offset Notes

Net Metering is only allowed up to 25kW

Offset Calc Tool
PV Watts

Metering & disconnect

Production Meter Required
Situational
Production Meter Criteria
  • Over 25kW requires production meter
  • Taps require an unprotected production meter which comes before the fused disconnect
Meter Spot Process

Temporary Disconnect Reconnect Process (TDR) Call our office at to schedule this disconnect. Please allow a day or two for scheduling purposes. At this time there are no costs for the TDR.

TDR - Who to

TDR - Applications/Documents Req N/A

TDR - ETA of notice required for request 2 days

TDR - Who can schedule? Does not matter

TDR - ETA of Utility Scheduling TDR N/A

Allowed Meter Adapter
None

Plans & docs

SLD Reqs

All Jobs

  • Detailed one-line diagram of the proposed facility, all applicable elementary diagrams, major equipment, (generators, transformers, inverters, circuit breakers, protective relays, etc.) DER Samples Attached
Electric Service Reqs

Any MPU, sub panel, or tap will require a whole house disconnect

Install Reqs

Utility will set the meter into the meterbase. They do not allow floating connections such as insulating piercing connectors nor Polaris type lugs to be used.


Utility Inspection Required

Rate Schedule Link
link
Website
link
Phone
(800) 879-0339

Other details

Restrict Inspection
0
Address ID
358684
Express Planset Eligible
No