City of Roodhouse

Illinois Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Energy generated by the customer-owned generator during the billing period may supply all or a portion of the energy required by the customer's load. The customer shall be credited for excess energy delivered by the customer to the City at the meter from the approved facility. Customer will be credited at the avoided cost (avoided cost amount unavailable)

Rebates Offered
0
Deregulated
1
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Systems must be properly sized to not exceed the customers expected annual usage based on current needs of the customer. Energy usage will be analyzed using the last 36 months of energy usage (if available) to calculate the customer expected annual usage.


If the customer provides documentation specifying why the usage has increased over that time, such as home renovation/addition or installation of electric heating of an EV charging station, then the previous 12-month period shall be used to determine the average for the expected annual usage.


If the applicable months of data are not available for an individual customer, the average usage amounts by other similar customers of the utility, as determined by the utility, shall be used to set the expected annual usage.

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch

Plans & docs

Site Plan Reqs

Standard (not required for interconnection)

SLD Reqs

Standard - see example uploaded to files

Electric Service Reqs

IEEE 1547

IEEE 519-2014

IEEE 1453

UL 1741

NESC

ANSI/NFPA 70

OSHA

Install Reqs

AC Disconnect Required, must be 24/7 readily available and lockable

Electrical Stamp Required
0
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0

Other details

Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with City of Roodhouse before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.