Irwin EMC
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
If the electricity supplied by the Cooperative and consumed by the Member Generator during the Billing Period exceeds the electricity generated by the Member’s DG Facility and supplied to the Cooperative during the Billing Period, then all electricity generated by the Member Generator and supplied to the Cooperative shall be deemed to have been used by the Member Generator and set off against the electricity supplied by the Cooperative. If the electricity generated by the Member Generator and supplied to the Cooperative during the Billing Period exceeds the electricity supplied by the Cooperative and consumed by the Member Generator, then the Excess Net Energy shall be purchased or credited by the Cooperative at the avoided cost of $0.04
- Rebates Offered
- 0
- Allows Standby
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- 0
System size & offset
- System Size Restrictions
- 10
- System Size Restriction Type
- AC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Peak generating capacity of not more than 10kw for a residential application and 100kw for a commercial application; Is intended primarily to offset part or all of the Member Generator’s requirements for electricity
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- Situational
- Production Meter Criteria
Production meter only required if customer chooses a buy all sell all billing option (this will be rare, if any)
- Production Meter Position
- Inv-Disco-PM-POI
- Production Meter Labeling
- Production Meter
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Visible Lockable Labeled Disconnect
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
Site Plan not required for IX submittal
- SLD Reqs
See One Line Diagram Examples uploaded to files (page A20 in DGEN_Procedure)
- Install Reqs
- Must install a UL approved, visible load break disconnect switch (per NEC 705)
- Disconnect required signage (please see placards section)
- Visible break disconnect shall be adequately sized for the installation and of load break type.
- Visible break disconnect shall be readily accessible, and should be located outside within 5 feet of the meter. It shall have a means to be locked in the open position by Cooperative personnel.
- Visible break disconnect shall be equipped for installation of a Cooperative padlock for locking switch in open position.
- Installation shall meet all applicable NESC, NEC and local codes.
- Placards
AC Disconnect
- Signage shall be placed by the Member Generator at the Isolation Disconnect Switch indicating the purpose of the switch along with contact names and numbers of the Member Generator and the Member Generator’s “Operator in Charge.”
- Electrical Stamp Required
- 1
- Equipment Approvals
- California Energy Commission
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Phone
- (229) 468-7415
Other details
- Restrict Inspection
- 0
- Revision Required
- 1
- Mod Swap Requires Planset
- 1
- Address ID
- 6991614
- Express Planset Eligible
- No