Carroll EMC
Net Metering Allowed1
NEM TypeMonthly
Supply Side Taps Allowed1
Line Taps Allowed1
Load Taps Allowed1
AC Disconnect RequiredYes
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
Production that exceeds the customers' monthly usage will be credited at the Excess Generation Rate.
June - September $.0551 per kWh
December - February $.0460 per kWh
All Other Months $.0442 per kWh
- Rebates Offered
- 0
- Deregulated
- 0
- Allows Standby
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Supply Side Taps Allowed
- 1
- Line Taps Allowed
- 1
- Load Taps Allowed
- 1
- Tap Criteria
- Line Side Taps allowed but not in meter can
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 10
- System Size Restriction Type
- AC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
- Offset Calc Tool
- PV Watts
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Utility Disconnect Switch
- Meter Spot Process
We install a bidirectional meter and meter the forward energy and reverse energy.
Temporary Disconnect Reconnect Process (TDR): Call to schedule a disconnect (one day in advance please)
TDR - Who to Contact: Customer service
TDR - Applications/Documents Req: N/A
TDR - ETA of notice required for request: 1 Day
TDR - Who can schedule? Customer
TDR - ETA of Utility Scheduling TDR: 1 Day
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
- Devices such as the service panel, disconnect switch, inverters, generators, circuit breakers, etc. must contain the electrical rating and operating voltages.
- SLD Reqs
All Jobs
- "A positive means of disconnecting and locking out the Member Generator-owned generation equipment with visible air-gap shall be provided to insure safety of Cooperative operating personnel during line maintenance. This disconnecting means may be via a lockable air-break disconnect or by a lockable draw out circuit breaker."
Line Side Taps
- Review Tap Criteria
Batteries
- Both PV and Batteries need to wire through a single disconnect
- Use a Generation Disconnect when able to and to use an upstream disconnect when we need to split PV
- Install Reqs
- Equipment Approvals
- California Energy Commission
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Rate Schedule Link
- link
- Website
- link
- Phone
- (770) 832-3552
Other details
- Restrict Inspection
- 0
- Address ID
- 199492
- Express Planset Eligible
- Yes