Canoochee EMC
Net Metering Allowed1
NEM TypeAnnual
Supply Side Taps Allowed1
Line Taps Allowed0
Load Taps Allowed1
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Annual
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Solar Export Type
- Avoided Cost
- Solar Export Rate Approx
- 0.035
- Net Excess Generation Notes
The generated energy fed into the Cooperative's electric grid will be purchased by the Cooperative the avoided cost rate.
- Rebates Offered
- 0
- Allows Standby
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 1
- Supply Side Taps Allowed
- 1
- Line Taps Allowed
- 0
- Load Taps Allowed
- 1
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 10
- System Size Restriction Type
- AC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
Metering & disconnect
- Production Meter Required
- No
- Meter Spot Process
NOTICE - utility will NOT allow any means of interconnection between the meter and the first means of disconnect.
TDR Process
Contact - staff (x2027)
Notice Req. - 24hr notice preferred, but typically can do same-day
Who can schedule?
Reconnect: must be called before 3PM to have reco completed (5pm is latest they will come out)
- Allowed Meter Adapter
- None
Plans & docs
- SLD Reqs
NOTICE - utility will NOT allow any means of interconnection between the meter and the first means of disconnect
(TEST PROJECT WITH GATEWAY 3 INTERCEPTING UM https://portal./projects/506117/task/10989001)
- Website
- link
- Phone
- (800) 342-0134
Other details
- Restrict Inspection
- 0
- Revision Required
- 0
- Mod Swap Requires Planset
- 1
- Address ID
- 209126
- Express Planset Eligible
- Yes