Lake Worth Beach Electric Utility

Florida Utility Interconnection & net metering rules
Net Metering Allowed1
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
Post Solar Billing Method
Net Metering
Rebates Offered
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Percentage
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
System Size Justification
Load Justification
System Offset Notes
  • Load Justification Form required on All projects
  • We only allow installations up to 10KW Max.
  • The system can’t produce more KWH’s than the property consumed for the previous 12 months  
  • The GPR shall not exceed ninety percent (90%) of the Customer’s electric distribution service rating. If the GPR does exceed the ninety percent (90%) limit, the Customer shall be responsible for all costs associated with upgrading the distribution service to ensure the ninety percent (90%) limit is not exceeded.  
Offset Calc Tool
N/A

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Website
link
Phone
(561) 533-7300

Other details

Restrict Inspection
0
Address ID
136325
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Lake Worth Beach Electric Utility before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.