SLVREC - San Luis Valley Rural Electric Cooperative
Net Metering Allowed1
Line Taps Allowed0
Load Taps Allowed0
Net metering & export
- Net Metering Allowed
- 1
- Post Solar Billing Method
- Net Metering
- Rebates Offered
- 0
- Allows Standby
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 25
- System Size Restriction Type
- DC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- Combination
- Offset Value
- 120
- Offset Calculation Basis
- Historical
- Offset Calculation Period
- 12
- Industry Standard Watts Sqft
- 2
- System Offset Notes
120% of the previous 12 months electric energy consumption up to 25kW.
- Offset Calc Tool
- N/A
Metering & disconnect
- Allowed Meter Adapter
- None
Plans & docs
- SLD Reqs
- Production Meter required.
- Inverter > Disco > PV Meter > POI
- Install Reqs
DG facilities require two meters in accordance with the Net Meter Distributed Generation Guideline. A $100 meter fee is also required for each DG facility. DC Facilities must be installed "behind the meter" on a new or existing electric service supplied by the Cooperative.
- Website
- link
- Phone
- (719) 852-3538
Other details
- Restrict Inspection
- 0
- Address ID
- 136331
- Express Planset Eligible
- Yes