Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

Sangre de Cristo Electric Association

Colorado Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
1
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

In months when the consumer generates more electricity than is consumed by the consumer, the Association will carry forward to the next month a kWh credit balance for the net energy received. The consumer will be billed by the association for the service availability charge and the other applicable charges of the appropriate rate schedule but with zero kWh usage for the month. For Net Meter/TOU consumers, kWh credit balances will carry forward in the respective time period (on-peak and/or off-peak)

Rebates Offered
0
Deregulated
0
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
10
System Size Restriction Type
DC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes


Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • Equipment shall not be installed on any utility-owned equipment or poles
  • Equipment must be a minimum of 10 ft from any utility-owned equipment or poles
  • Disconnect must be accessible to the utility 24/7 - it cannot be fenced in, locked away, or enclosed in any way that blocks access.
SLD Reqs


Install Reqs


Electrical Stamp Required
0
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Website
link
Phone
(719) 395-2412

Other details

Restrict Inspection
0
Address ID
173755
Express Planset Eligible
No
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Sangre de Cristo Electric Association before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.