Report a correction Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes
Net metering & export
- Net Metering Allowed
- Yes
- NEM Type
- Monthly
- TOU Utility
- Yes
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
In months when the consumer generates more electricity than is consumed by the consumer, the Association will carry forward to the next month a kWh credit balance for the net energy received. The consumer will be billed by the association for the service availability charge and the other applicable charges of the appropriate rate schedule but with zero kWh usage for the month. For Net Meter/TOU consumers, kWh credit balances will carry forward in the respective time period (on-peak and/or off-peak)
- Rebates Offered
- No
- Deregulated
- No
- Allows Standby
- No
Interconnection & taps
- Approval Req To Install
- Yes
- Line Taps Allowed
- No
- Load Taps Allowed
- No
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 10
- System Size Restriction Type
- DC kW
- System Size Battery Included
- No
- System Size Includes Existing Systems
- No
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Metering & disconnect
- Production Meter Required
- Yes
- Production Meter Position
- Inv-Disco-PM-POI
- Production Meter Labeling
- Production Meter
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Visible Lockable Labeled Disconnect
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
- Equipment shall not be installed on any utility-owned equipment or poles
- Equipment must be a minimum of 10 ft from any utility-owned equipment or poles
- Disconnect must be accessible to the utility 24/7 - it cannot be fenced in, locked away, or enclosed in any way that blocks access.
- SLD Reqs
- Install Reqs
- Electrical Stamp Required
- No
- Meter Num Req SLD 3LD
- No
- ESID Num Req SLD 3LD
- No
- Website
- link
- Phone
- (719) 395-2412