Net Metering AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
No
TOU Utility
No
Post Solar Billing Method
Export Rate
Solar Export Type
Fixed kWh
Net Excess Generation Notes

With qualifying customer owned small power producing systems and to credit any excess power beyond what the customer-owner of the facility consumes in any given month toward the customer's future monthly bills, an arrangement known as net metering. Further, such utilities are required to purchase any annual excess power produced by the facility. In the case of municipally owned utilities, the annual excess power may be credited to the customer in a manner deeped appropriate by the utlity.

Rebates Offered
No
Deregulated
No
Allows Standby
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
10
System Size Restriction Type
DC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Up to 10 kW DC

Metering & disconnect

Allowed Meter Adapter
None

Plans & docs

SLD Reqs
  • Production meter required
Website
link

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes