Net Metering AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
No
TOU Utility
No
Post Solar Billing Method
Export Rate
Net Excess Generation Notes

WGC allows customers to install solar on their site and use the energy generated from the site to power their home. When the solar panels produce exactly what the customer uses, there will be no energy charges added to the customer’s bill (all applicable fees and taxes will apply and must be paid monthly). During times when the solar panels produce more electricity than the customer uses, the net surplus that flows back to the power grid is credited at the WGC rate - $0.04 cents per kilowatt hour. When the solar panels don’t produce enough power for the customer’s home, WGC customers will pay the same rate as other LID electric customers.

If the energy produced by the system is greater than the energy you are using at that time, then the excess energy produced is credited to that month’s bill at the WGC rate - $0.04 cents per kilowatt hour.

Rebates Offered
No
Deregulated
No
Allows Standby
Yes

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
Percentage
Offset Value
125
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
Utility Specific Adjustments
  • It is recommended to size the system below 20 kW AC as going over 20 kW will have longer timeline (at least 6 months) and fee of $1,800.00
System Offset Notes


Offset Calc Tool
CSI

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-PM-Disco-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
Tesla Backup Switch

Plans & docs

Site Plan Reqs

All Projects

  • Production Meter and Disconnect must be located in front of fence for 24 hour access
SLD Reqs

Existing Systems

  • Existing (N) and (E) systems must be combined to share one production meter. This includes battery projects
Electrical Stamp Required
No
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Website
link
Phone
209-323-5000 ext. 1417

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes