Supply Side Taps AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Rebates Offered
No

Interconnection & taps

Approval Req To Install
Yes
Supply Side Taps Allowed
No
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
Percentage
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
3
System Offset Notes

- Customer-Generators may install systems no larger than 100% of the last 12 months of energy use recorded by the electric meter.

- Residents with less than 12 months of energy use may use 3 kWh per square foot as the maximum allowed using the Developed Building square footage from the on-line Property Report. https://roseville.maps.arcgis.com/apps/webappviewer/index.html?id=2a67e5a4e1cc4f489868b6563589bf19

Offset Calc Tool
CSI

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

Battery Jobs:


  • Roseville Electric requires an AC disconnect for each interconnected source.
  • The AC disconnect must be within sight of the main electric panel, within 5' of the main electric panel, and have a visible open disconnect device
  • Provide load calculations for the backup load center (and ensure all appliance/equipment with wattages are indicated)
Electric Service Reqs

SOLAR READY MPU's NOT ALLOWED PER UTILITY

Install Reqs

## SOLAR READY MPU's NOT ALLOWED PER UTILITY


Projects installed without interconnection approval are subject to being fined, and may be locked off until the required documentation is submitted and the Approval to Interconnect (Form D) is signed by Roseville Electric Utility.

Website